Saturday 30 November 2013

Photos

Managed to take some photos today - stairs have still not been finished and kitchen has been delivered but it is still in bits and pieces


Front door


 Laundry door


Front facade - front door and no scaffolding

Kitchen in pieces


Photos of stairs



Wednesday 27 November 2013

Everything is coming together

Just a quick update. Stairs have been installed and they look fantastic. Pity Genneral Stairs ran out of balustrades - some how they were three boxes short so I will post pics later this week.

Carpenter turned up yesterday and installed all the doors and most of the skirtings/architraves.

Kitchen should be delivered end of this week. Finally I can see it all coming together after waiting 9 months (that is when we had our appointments with the kitchen/bathroom/colour consultants).

I met with our Site Supervisor yesterday and we are now two days behind schedule. So far so good. Hope we can move in some time in February.

Saturday 16 November 2013

Gyprocking is up - some photos


Entrance


Main living area - room for future fireplace


Kitchen - pantry and fridge space


Dining area


Home theatre with bulkhead


Multi room - with room for staircase


Bedroom 5 - downstairs (at front of house)


Upstairs rumpus - with bulkhead


Main bathroom


Main bathroom - shower niche


Main bedroom



Bedroom 2 - upstairs front of house


Tuesday 12 November 2013

Finally at lining stage

Finally we have had an inspection from Tyrells and the statuory authority. There are a few minor things but our SS is attending to that.

Airconditioning drama is over, they had to move the wardrobe in Bedroom 2 to the other side of the room, but at least there will be a usuable wardrobe. The upstairs rumpus is now quite small as they had to put two stack points in together with a bulkhead but at least that will gives us some storage space (bookshelves).

Here is two recent photos taken over the weekend


The porch beam has been painted the wrong colour. It should be ironstone, not surfmist.