Contract Time Line

36 week contract


Week 1 - Friday
14/6/13     Contract officially begins
17/6/13     No action
18/6/13     No action
19/6/13     No action
20/6/13     Our file is now officially in construction phase

Week 2
21/6/13     No action
24/6/13     Gravel delivered
25/6/13     Excavation
26/6/13     No action
27/6/13     No action - rain

Week 3
28/6/13     Silt fence erected - rain in the afternoon
1/7/13       Fence is erected - block to wet
2/7/13       No action - block too wet
3/7/13       No action - block too wet
4/7/13       No action - block too wet

Week 4
5/7/13      No action - block too wet
8/7/13      No action - email received re: delay in concreting block too wet
9/7/13      rain - block too wet
10/7/13    No action - block too wet - sunny day
11/7/13    No action - block too wet - sunny day
9 days of  rain claimed according to SS

Week 5
12/7/13   No action - block too wet -sunny day
Block has been cleared a bit to help drain the water
15/7/13   Piering - inspection from engineer
16/7/13   Formwork started
17/7/13   Drainage started, pods delivered
18/7/13   Formwork, drainage, pods completed

Week 6
19/7/13  Slab laid
22/7/13  Slab curing - Steel delivered
23/7/13  External drainage
24/7/13  Slab curing
25/7/13  Slab curing

Week 7
26/7/13 no action
29/7/13 no action
30/7/13 frames delivered
31/7/13 no action
1/8/13 more frames, flooring system delivered

Week 8
2/8/13 no action - carpenters out on block late pm
3/8/13 ground floor frames started
5/8/13 windows delivered
6/8/13  upper floor frames delivered
7/8/13 ground floor windows in, floor system installed
8/8/13 upstairs frames, roof trusses, windows installed

Week 9
9/8/13   internal plumbing, gas points
12/8/13 bricks delivered
13/8/13 delivery of supplies for bricklayer, sand, etc
14/8/13 meter box installed
15/8/13 concrete grinding complete, bricklayers started, staircase window installed

Week 10
16/8/13 bricklayers, plumbing, site inspection
19/8/13 bricklayers
20/8/13 bricklayers/scaffolding delivered
21/8/13 bricklayers
22/8/13 scaffolding up/roof tiles delivered


Week 11
23/8/13 gutters/fascia
26/8/13 no action

27/8/13 Upper roof tiles
28/8/13 Upper roof tiles
29/8/13 Bricklayers are back

Week 12
30/8/13 bricklayers
2/9/13   bricklayers
3/9/13   bricklayers
4/9/13   bricklayers
5/9/13   bricklayers

Week 13
6/9/13   bricklayers
9/9/13   bricklayers - material for cladding and eaves delivered
10/9/13 bricklayers - carpenters for eaves
11/9/13 bricklaying finished, upper eaves installed
12/9/13 box guttering - bedroom 5

Week 14
13/9/13 brick cleaning
16/9/13 expansion joints, rain in the afternnon
17/9/13 brick inspection, no work done, rain in afternoon
18/9/13 painting upper eaves
19/9/13 painting upper eaves and downpipes

Week 15
20/9/13 no action
23/9/13 we were holidays - porch was installed
24/9/13 not sure
25/9/13 lower roof gutter and eaves
26/9/13 lower roof gutter and eaves

Week 16
27/9/13 lower roof tiling
30/9/13 no action
1/10/13 porch roof measured
2/10/13 internal garage bricks cleaned, eaves,cladding material delivered
3/10/13 no action

Week 17
4/10/13 working on lower roof
5/10/13 electrical rough in
7/10/13 public holiday
8/10/13 lower eaves, porch
9/10/13 electrical, more brick cleaning
10/10/13

Week 18
11/10/13 carpenter - finish front porch
13/10/13 back cladding, plasterer came in to measure
14/10/13 porch metal roof
15/10/13 articulation joins, rainwater tank installed
16/10/13
17/10/13 rainwater tanks delivered

Week 19
18/10/13 no action
21/10/13 bricklayer finished post on porch/airconditioning plans approved
22/10/13 no action
23/10/13 no action
24/10/13 no action

Week 20
25/10/13 airconditioning fitout
28/10/13 no action - waiting for variation for moving wardrobe in Bed 2
29/10/13 no action
30/10/13 no action
31/10/13 met with SS on site, moving water tanks discussed with plumbers

Week 21
1/11/13 no action
3/11/13 carpenter
4/11/13 no action
5/11/13 no action
6/11/13 Tyrells and statuory authority inspection
7/11/13 carpenter, lower gutters, eaves and porch post painted

Week 22
8/11/13 insulation
11/11/13 gyprock
12/11/13 gyprock
13/11/1  gyprock
14/11/13 gyprock

Week 23
15/11/13 gyprock
18/11/13 gyprock sanded, front scaffolding removed, cornices delivered
19/11/13 cornices installed
20/11/13 cornices installed
21/11/13 no action

Week 24
22/11/13 roof plumbers
25/11/13 stairs
26/11/13 carpenter - architraves/skirting
27/11/13 doors delivered
28/11/13 carpenter (doors hung) and waterproofing

Week 25
29/11/13 kitchen delivered
2/12/13 kitchen installed/stairs
3/12/13 kitchen installed
4/12/13 range hood installed
5/12/13 can't remember

Week 26
6/12/13 tiles delivered
9/12/13 tiling
10/12/13 tiling
11/12/13 tiling
12/12/13 tiling

Week 27
13/12/13 tiling (grouting)
16/12/13 no action
17/12/13 benchtops, garage doors, floor sanded
18/12/13 inspection with SS
19/12/13


Week 28
20/12/13 a big rubbish clean out
23/12/13
24/12/13 carpenter - skirting family area
25/12/13 public holiday
26/12/13 public holiday

Week 29
27/12/13 to 2/1/13
XMAS break

Week 30
3/1/14 XMAS break

Week 31
10/1/14 XMAS break
13/1/14 XMAS break
14/1/14 XMAS break
15/1/14 painters - prepping
16/1/14 painters - spray undercoat
17/1/14 painters - spray undercoat

Week 32
20/1/14 SS marking out plasterers mistakes
21/1/14 plasterer
22//1/14 no action
23/1/14  no action

Week 33
24/1/14 plasterer sanding
27/1/14  no action - public holiday
28/1/14 painters
29/1/14 painters
30/1/14 painters

Week 34
31/1/14 painters - front door varnished
3/2/14  painters - stairs stained - top coat interior walls
4/2/14 painters finished today -  stair case varnished, skirting boards painted
5/2/14 electrical fitout/plumbing fit out -baths/taps installed
6/2/14 electrical fitout


Week 35
7/2/14 electrical fitout
10/2/14 airconditioning
11/2/14 wardrobe/cupboard fitout
12/2/14 main living/dining/kitchen tiling, splash back tiling
13/2/14 no action


Week 36
14/2/14 1 shower screen installed, mirror installed in powder room and ensuite
15/2/14 carpenter installing locks
17/2/14 meeting on site with SS, hopefully WILL GET THE KEYS IN THREE WEEKS (10/3)
18/2/14 bamboo flooring installed, house cleaned inside - bathroom, benches, windows
19/2/14 no action
20/2/14 towel ring installed, plumber for downpipes

Week 37
21/2/14 no action
24/2/14 carpet
25/2/14 carpet, fencing removed, site clean
26/2/14 carpenter to finish skirting
27/2/14 no action

Week 38

28/2/14 termite reticulation started,  SS - blue stickers RAIN DAY
3/3/14  termite reticulation system installed
4/3/14  floor tiling finished, kitchen splash back changed, alfresco tiles laid
5/3/14
6/3/14 driveway excavated/concrete slab for rainwater tank extended

Week 39
7/3/14 Steel mesh driveway
10/3/14
11/3/14 driveway
12/3/14 Painters return
13/3/14 Painter - staircase stained

Week 40
14/3/14 - SS onsite - updated us on build. Possible PCI next Friday
17/3/14 - tilers to finish main bathroom and tiles laundry, front door
18/3/14 - Local inspection
19/3/14 - water tank moved
20/3/14 - Tyrells inspection - tiler - shower screen started

Week 41
21/3/14 - PCI inspection
22/3/14 - tiler
24/3/14 - airconditioning unit installed, appliances installed, electrician
25/3/13 - garage cleared for epoxy slab

31.3.14  - SETTLEMENT