Sunday 21 July 2013

Formwork and Slab

The slab was laid on Friday 19 July. The concreters started work at 7.30am and they only had one hour left of work in the afternoon and it started to rain. The SS mentioned that he will have a look at the slab on Monday and they may have to grind the garage slab  before the brickwork starts and towards the end they may have to top up the garage slab.